Wednesday, October 7, 2009

Day 97: Preparation for interior plastering

We spent the day doing the following tasks in preparation for interior plastering.
  • Completed cutting and installing diamond mesh metal lath to the interior edge of the top plate and around the entry door
  • Completed applying plastic sheet and masking tape to the curved beams and electrical boxes
  • Fabricated blocks that simulate the windowsills during plastering. These blocks are needed because the wood that will be used to fabricate windowsills will not be dry and ready to finish until summer, 2010. They will allow the plaster to be molded around where the windowsills will eventually mount.
  • Swept the walls to remove any loose debris
  • Swept the floors to remove a month’s worth of construction debris
  • Started applying masking tape and plastic sheet around the perimeter of the building
I'll close with two pics of the redwood casing I mentioned in Tuesday’s post. Thanks for reading. I appreciate your comments.




Wednesday, September 30, 2009

Day 92: Drywall joint compound and plaster preparation

The Consolidated Drywall folks applied joint compound to the drywall seams, screws and electrical box openings. Here is a pic looking east from the kitchen.

More plaster preparation tasks completed today:
Thanks for reading. I appreciate your comments.

Monday, September 28, 2009

Day 90: Plaster preparation

We did more plaster preparation tasks again Monday.
  • Joshua completed installing diamond mesh metal lath around the interior window frames
  • I applied masking tape and protective paper to 2 ledgers to prevent plaster contamination
  • Trevor set up scaffolding along the east wall
  • Trevor applied masking tape and plastic sheet to the exterior of the east windows and soffit
Here is a pic of the east wall almost ready for plastering

The spiral staircase from Stocklin Iron in Santa Rosa, CA was delivered today.

Thanks for reading. I enjoy reading your comments.

Saturday, September 26, 2009

Day 89: Plaster preparation, continued

We are getting closer to being ready for plastering. Here is the list of plaster preparation tasks we worked on Friday.
  • Trevor continued filling electrical and plumbing channels in the walls to provide a level surface for plastering
  • Joshua continued applying diamond mesh metal lath to the interior windows
  • I completed applying foam insulation to cracks and holes in the walls
  • Trevor applied masking tape and plastic sheet to the northeast corner windows to keep plaster off the glass and frames
  • Trevor installed a metal door and frame over the fire sprinkler valve on the north wall
  • Trevor removed soil from the east wall to a point approximately 6 inches below the final grade
To prepare for erosion control during winter rains, I spread, raked in and watered seed on the steeper slopes. I look forward to seeing it sprout in the coming weeks. Thanks for reading. I appreciate your comments.

Tuesday, September 22, 2009

Day 86: More plaster preparation

I worked late today, so I am just posting a quick list of what was done.
  • Joshua completed installation of diamond mesh metal lath to the exterior of all windows, and to the interior of one window
  • I installed spray foam insulation around the interior of several 2nd story windows
  • Trevor continued to fill the slots containing electrical wiring and plumbing pipes with mortar
  • Marty tested spraying drywall joint compound and veneer plaster on the interior walls. More to come before the final decision on an interior finish.
Thanks for reading. I enjoy reading your comments.

Thursday, September 17, 2009

Day 83: Swales, plaster preparation and another retaining wall

Steve completed creating 2 swales; one to the east (uphill) of the home and one to the west (downhill). I will plant fruit and nut trees in the downhill sides of the swales. Winter stormwater surface runoff is slowed down, spread out and sunk into the soil by a swale. Soil under a swale will still have water in the drought season after surrounding soil has dried out. This will reduce the amount of irrigation water needed for the fruit and nut trees. The east swale will reduce the amount of surface storm water reaching the home. The west swale will reduce the amount of surface water running off the property from the south yard. Here is a pic of the east swale.

Some of the other tasks started or completed today:
  • In preparation for plastering, Joshua cut and installed pieces of diamond mesh metal lath to the exterior of several windows.
  • Justin applied weatherproofing to several second story windows
  • I applied foam insulation around the interior of several windows
  • Alan Dodd of Live Oak Design delivered beautiful doors for the bedroom, bathroom, closet and entry. Alan is also building the kitchen cabinets. All of the wood used is FSC certified.
  • Erik installed some Cat5 cables and began working on a conduit to run audio wiring from the north to the south side of the family room
  • Trevor waterproofed the southwest retaining wall we built yesterday
  • Trevor built a small retaining wall on the northwest corner of the utility room. The retaining walls were built from leftover pieces of APEX block.