Saturday, September 26, 2009

Day 89: Plaster preparation, continued

We are getting closer to being ready for plastering. Here is the list of plaster preparation tasks we worked on Friday.
  • Trevor continued filling electrical and plumbing channels in the walls to provide a level surface for plastering
  • Joshua continued applying diamond mesh metal lath to the interior windows
  • I completed applying foam insulation to cracks and holes in the walls
  • Trevor applied masking tape and plastic sheet to the northeast corner windows to keep plaster off the glass and frames
  • Trevor installed a metal door and frame over the fire sprinkler valve on the north wall
  • Trevor removed soil from the east wall to a point approximately 6 inches below the final grade
To prepare for erosion control during winter rains, I spread, raked in and watered seed on the steeper slopes. I look forward to seeing it sprout in the coming weeks. Thanks for reading. I appreciate your comments.

Tuesday, September 22, 2009

Day 86: More plaster preparation

I worked late today, so I am just posting a quick list of what was done.
  • Joshua completed installation of diamond mesh metal lath to the exterior of all windows, and to the interior of one window
  • I installed spray foam insulation around the interior of several 2nd story windows
  • Trevor continued to fill the slots containing electrical wiring and plumbing pipes with mortar
  • Marty tested spraying drywall joint compound and veneer plaster on the interior walls. More to come before the final decision on an interior finish.
Thanks for reading. I enjoy reading your comments.

Monday, September 21, 2009

Day 84 & 85: Final grading and plaster preparation

Joshua, Justin and I ran a successful test of a Tirolessa plaster gun on Friday. We shot the northeast corner wall with a coat of NHL 3.5 lime plaster from Saint Astier. Here is a vid of the gun in action.



Steve completed final grading around the home on Friday and Monday. Here is a pic of the home from the southwest.

Some of the other tasks started or completed Friday and Monday:
  • Trevor waterproofed the utility room retaining wall built Thursday
  • Justin and I completed application of weatherproofing on all windows
  • Joshua and I installed diamond mesh metal lath to the exterior of several more windows
  • I trimmed excess foam insulation around the interior of several windows
  • Erik completed all rough electrical wiring inside the home
  • Marty and Trevor filled slots containing electrical wiring and plumbing pipes with mortar to provide a uniform surface for plastering
  • Justin and Marty installed a vent pipe for the bathroom ventilation fan
I’ll close with a pic of Cindy cutting down scotch broom with her new electric hedge trimmer over the weekend. Thanks for reading. Please feel free to comment.

Wednesday, September 16, 2009

Day 82: Insulation, grading and garden wall

The folks from Tri County Insulation finished spraying foam insulation today. They completed a 7 inch average thickness application in the entire ceiling. The R-value of the 7 inch layer is approximately 40.

Tri County Insulation also installed UltraTouch batt insulation in the interior stud walls. This insulation will reduce sound transmission between the bedroom, bathroom and family room.

Steve continued doing a great job grading and shaping the landscape while Justin, Trevor and I built a small garden wall by the southeast corner of the home. The wall will prevent collapse of the east hillside in front of the bedroom patio door.

Green comment for today:
Consider using UltraTouch batt insulation from Bonded Logic to insulate your wall or ceiling cavities. The advantages compared to typical fiberglass batt insulation are:
Thanks for reading. Please feel free to leave a comment.

Tuesday, September 15, 2009

Day 81: Insulation, grading and site cleanup

The folks from Tri County Insulation continued spraying foam insulation today. They completed a 5-1/2 inch thick application in the ceiling over the family room.

Steve and Trevor completed placement of all the underground pipes and drain lines today. Steve began to do final site grading. It is nice to finally have a normal step down from the porch and patio doors. Here is a pic from the southwest followed by one from the west.


Raphael cut the remaining large logs on the site into smaller pieces ready to split for firewood while I sorted leftover items from construction into various piles. Thanks for reading. I appreciate your comments.

Monday, September 14, 2009

Day 80: Insulation

The folks from Tri County Insulation started spraying foam insulation in the ceiling over the kitchen. Here is a pic showing the first 5-1/2 inch thick application.

Green comment for today:
Consider using a soy based spray foam insulation like BioBased to fill your wall or ceiling cavities. Insulation R-value per inch is equal to or greater than common fiberglass batt material and air leakage is lower than with any other type of insulation. BioBased replaces a portion of the petroleum product with natural renewable oil and blows the material with water resulting in a more environmentally friendly product than common polyurethane spray foam insulation.

Thanks for reading. I enjoy your comments.

Monday, June 29, 2009

Day 35: Wall lift #2

We did some final preparations for wall lift #2 in the morning.
  • Positioned a seat for a porch roof beam.
  • Hung a pressure treated ledger for the loft from the east wall.
  • Finished placing all vertical rebar.
  • Placed J-bolt supports for the utility room north wall top plate.
  • Filled any gaps larger than 3/8 inch in the walls and around window bucks with closed cell spray foam to prevent grout from leaking out during the pour.
  • Added a few more metal bands around ledgers to keep them snug against the wall during the pour.
Pacific Coast Concrete Pumping and Las Anamas Concrete showed up after lunch.

The calm before the pour.

Justin and Marty getting ready for the hose.

Joshua, Justin, Marty and Trevor filled, consolidated, managed the hose and cleaned up - repeated for about 100 cores.

Raphael, doubling as Integral Construction staff photographer, was busy shooting photos.

I got to fill a few cells in the utility room.

We had another successful pour with no blowouts. Thanks for reading. I enjoy your comments.

Wednesday, June 17, 2009

Day 27: Preparing for a lift

Today we prepared the walls for the first grout lift. Grout fills the interconnected horizontal and vertical network of cells inside the APEX blocks creating the building structure once the concrete is cured. A lift is the height the grout will be poured at one time. In this case, the lift is 5 courses (approximately 80 ionches). The grout is a thin concrete mix and can leak out through holes and gaps in the walls and bucks. The grout applies hydrostatic pressure on the walls and bucks. This pressure increases towards the bottom of the wall just as water pressure against your body increases the deeper you dive. Corners and thin areas of APEX block are most vulnerable to a phenomenon called blowout – when the grout fractures a portion of the wall material and begins gushing from the opening. We want to do everything we can to avoid blowouts. Some of the things that were completed today:
  • Plumbing vents and drains that penetrated partially into APEX grout cells were surrounded with foam, sealed and supported so that grout would not leak and the plumbing would be accessible in the future.
  • Small wooden forms were installed to properly locate 2 beam support brackets that must be cast into the grout during this lift.
  • Threaded rods were cut and placed into the window and door buck holes drilled yesterday.
  • Walls were shored up after ensuring they were vertical.
  • Made a final check to ensure window and door bucks were level and located properly in the openings.
  • All 6 exterior corners were shored up with a frame after ensuring that the walls were vertical.
  • Holes were drilled through the exterior 2 inch thick skin of APEX block under window openings to provide access for the concrete pump hose. All wall cells will be filled from the top of the 5th course of block, but these additional holes will ensure that grout is placed under the window openings.
  • Gaps around door and window openings and any gaps in the APEX block wall larger than about ¼ inch were filled with closed cell spray foam insulation. This material expands several times its size after being sprayed from the canister and fills the gap to prevent grout leaks.
Following are a couple pics from the end of day 27.


Thanks for reading. I appreciate your comments.