Thursday, October 22, 2009

Day 106: Exterior plastering…and solar panels

On Thursday, we applied the 2nd of 3 coats of lime plaster to the south wall.

The guys from Independent Energy Systems installed 22 Sharp 224 watt solar panels to the tilt racks on Tuesday - I totally forgot to take a picture. Below is a pic of the south wall showing the plaster and solar panels. Thanks for reading. I enjoy reading your comments.

Wednesday, October 21, 2009

Day 104 an 105: Exterior plastering

Monday we had the day off because of rain. On Tuesday, we applied the 2nd of 3 coats of lime plaster to the exterior of the east and west walls. This is called the straightening coat because the plasterers try to straighten out imperfections in the wall in preparation for the finish coat. I worked until 8:30 PM on this coat, so I didn't post Tuesday.

On Wednesday, we applied the 2nd of 3 coats of lime plaster to the exterior of the north wall. The final step is to scratch the coat to provide a mechanical key for the finish coat to latch onto. Here is a pic of the southwest corner of the home. Notice the difference between the horizontal scratched lines on the west wall (left) and the bumpy texture of the scratch coat on the south wall (right).

I’ll close with a pic of me in front of the west wall near the end of day 105. Thanks for reading. Please feel free to leave a comment.

Saturday, October 17, 2009

Day 103: Interior plastering and ceiling texture

On Friday Joshua, Trevor and I completed interior gypsum wall plastering. It is great to have all of the APEX blocks finally covered. Here is a pic of the sliding glass patio door on the bedroom south wall.

Marty applied and knocked down ceiling texture while Trevor, Raphael and I shuffled scaffolding around. Between the rain this week and the water evaporating from the plaster, the house is humid like Florida. Below is a pick of Marty up top with Trevor and Raphael below. Thanks for reading. I appreciate your comments.

Green comment for today:
When selecting finishes, especially those inside the home, consider the simplest materials with the least amount of additives. This will result in the best indoor air quality. For example, my interior wall finish is 99% gypsum plaster (plaster of Paris).

I chose to avoid premix or ready mix materials because they contain vinyl compounds which act as binders. Once applied, the Volatile Organic Compound (VOC) portion of the binder will evaporate into your home atmosphere potentially affecting respiration in folks with chemical sensitivities. It is true that the VOC concentration will reduce dramatically over time, but it is best to not allow the material in the home if it is not needed.

To determine what is in a product, look at the Material Safety Data Sheet (MSDS). This can be confusing when a manufacturer decides to include a series of products on one MSDS. You sometimes see the words "may contain one or more of the following" in the Composition/Ingredients section of the MSDS. In this case, you need to call technical support to see if the particular product you are interested contains any offending ingredients.

Thursday, October 15, 2009

Day 102: South wall interior plastering

The power was back on Thursday. We applied gypsum plaster to all surfaces of the south wall except in the bedroom. Here is a pic of the south wall in the family room and loft.

Thanks for reading. Please feel free to leave a comment.

Wednesday, October 14, 2009

Day 101: Power outage plastering

We had a rain delay on Tuesday as the remains of Super Typhoon Melor hit the California coast. The job site held up to the storm pretty well considering we had bare soil everywhere. Power was out at the site Tuesday and Wednesday. We rented a generator which ran the plaster mixer, work light and radio. The generator did not produce enough current to run the compressor, so we could not use the plaster sprayer. We plastered the east wall of the loft by hand and called it a day. Below is a pic of the wall taken from the southwest corner of the loft. Thanks for reading. I enjoy reading your comments.

Monday, October 12, 2009

Day 100: Interior plastering

On Monday we applied gypsum plaster to the interior north wall. It is nice to see the cold looking APEX blocks covered with a uniform finish. Here is a pic of the great room portion of the wall taken from the loft.

The guys from Independent Energy Systems were back again today to install another rack for the photovoltaic array. Thanks for reading. I appreciate your comments.

Saturday, October 10, 2009

Day 99: Interior plastering

On Friday we applied gypsum plaster to the interior west wall. Here is a pick of Marty, Raphael, Joshua and Ben in action.

Here is a pic of Cindy in the dining room on Saturday after the wall has partially dried.

Here is a closeup pic of the kitchen window bullnose. This detail gives the house a nice old-world feel. Thanks for reading. I enjoy reading your comments.

Thursday, October 8, 2009

Day 98: Solar install, shower and final preparations for interior plastering

The folks from Independent Energy Systems began installing the PV solar panel racks on the roof - pic 1 below. They also installed the inverter (left) in the utility room next to the main distribution panel (right) - pic 2 below.


Joshua poured mortar on the shower floor and created a surface that tapers down slightly from the outside edges to the drain.

We completed applying masking tape and plastic sheet around the perimeter of the building in preparation for interior plastering. Thanks for reading. Please feel free to leave a comment.

Wednesday, October 7, 2009

Day 97: Preparation for interior plastering

We spent the day doing the following tasks in preparation for interior plastering.
  • Completed cutting and installing diamond mesh metal lath to the interior edge of the top plate and around the entry door
  • Completed applying plastic sheet and masking tape to the curved beams and electrical boxes
  • Fabricated blocks that simulate the windowsills during plastering. These blocks are needed because the wood that will be used to fabricate windowsills will not be dry and ready to finish until summer, 2010. They will allow the plaster to be molded around where the windowsills will eventually mount.
  • Swept the walls to remove any loose debris
  • Swept the floors to remove a month’s worth of construction debris
  • Started applying masking tape and plastic sheet around the perimeter of the building
I'll close with two pics of the redwood casing I mentioned in Tuesday’s post. Thanks for reading. I appreciate your comments.




Tuesday, October 6, 2009

Day 96: West and north wall plastering

Today we applied the first of three lime plaster coats to the exterior of the west and remainder of the north wall. Thanks to Trevor, Raphael, Joshua, Ben, Georg and Justin for helping complete the first coat of exterior plaster in 3 days. Here is a pic of the northwest corner of the home.

Some other tasks from day 96:
  • I planed and sanded more of the reclaimed tongue and groove redwood flooring for use as casing molding. I ripped off about one inch from the tongue side of the boards.
  • Justin installed the casings around the exterior of the utility room and entry doors. The groove will hold the plaster in place next to the molding.
  • Installed 2X4 boards in the kitchen wall to support cabinets
  • Installed extensions on the bottom of the window bucks inside to: 1) control the thickness of plaster on the wall next to the windowsill (plaster screed), 2) support the windowsill and 3) act as a support for the apron under the windowsill
  • Started cutting and installing diamond mesh metal lath to the interior wall top plate
Stella status:
She is still growing, and her bark has gotten deeper. I caught her napping this afternoon. Thanks for reading. I appreciate your comments.

Monday, October 5, 2009

Day 95: South wall plastering

Today we applied the first of three lime plaster coats to the exterior of the south wall. This is known as a scratch coat. It has this name because it is usually scratched while still wet to create grooves for the next coat to latch onto. We do not have to scratch the plaster because the sprayer leaves a nice bumpy surface for the next coat. Thanks to Trevor, Raphael, Joshua, Georg and Ben for making the day go smoothly. Here is a pic of the plaster next to a sliding patio door.

We also installed the utility room door today.

I’ll close with a couple pics of Trevor’s daughter Zephyra showing her plastering technique. She visited today with mom and grandma. Thanks for reading. I enjoy reading your comments.


Sunday, October 4, 2009

Day 94: Exterior plaster

On Friday we applied the first of three lime plaster coats to the exterior of the east wall and part of the north wall. Here are pics of both walls respectively. Thanks for reading. I appreciate your comments.


Thursday, October 1, 2009

Day 93: Ubiquitous plaster preparation and other tasks

I’m running late tonight after a very busy day. Here is a list of the things that happened Thursday.
  • Had a successful interior gypsum plaster test in the closet
  • Indirect water heater was delivered
  • Shower floor was leveled
  • Hung the entry door and 2 interior doors
  • Finished applying masking tape and plastic sheet to all exterior windows and sliding patio doors
  • Rinsed the exterior of the east and north walls in preparation for plastering Friday
Following is a pic of the entry door. Thanks for reading. Please feel free to leave a comment.

Wednesday, September 30, 2009

Day 92: Drywall joint compound and plaster preparation

The Consolidated Drywall folks applied joint compound to the drywall seams, screws and electrical box openings. Here is a pic looking east from the kitchen.

More plaster preparation tasks completed today:
Thanks for reading. I appreciate your comments.

Tuesday, September 29, 2009

Day 91: Plaster preparation and shower enclosure

In the continuing saga of plaster preparation, Trevor started to set up scaffolding along the south and west walls. I applied masking tape and plastic sheet to the interior of all windows and all doors except one.

Trevor and Raphael installed HardieBacker 500 board to the shower enclosure. This material will support the shower tiles. Below is a pic looking at the south and west walls of the enclosure. Thanks for reading. Please feel free to leave a comment.

Monday, September 28, 2009

Day 90: Plaster preparation

We did more plaster preparation tasks again Monday.
  • Joshua completed installing diamond mesh metal lath around the interior window frames
  • I applied masking tape and protective paper to 2 ledgers to prevent plaster contamination
  • Trevor set up scaffolding along the east wall
  • Trevor applied masking tape and plastic sheet to the exterior of the east windows and soffit
Here is a pic of the east wall almost ready for plastering

The spiral staircase from Stocklin Iron in Santa Rosa, CA was delivered today.

Thanks for reading. I enjoy reading your comments.

Saturday, September 26, 2009

Day 89: Plaster preparation, continued

We are getting closer to being ready for plastering. Here is the list of plaster preparation tasks we worked on Friday.
  • Trevor continued filling electrical and plumbing channels in the walls to provide a level surface for plastering
  • Joshua continued applying diamond mesh metal lath to the interior windows
  • I completed applying foam insulation to cracks and holes in the walls
  • Trevor applied masking tape and plastic sheet to the northeast corner windows to keep plaster off the glass and frames
  • Trevor installed a metal door and frame over the fire sprinkler valve on the north wall
  • Trevor removed soil from the east wall to a point approximately 6 inches below the final grade
To prepare for erosion control during winter rains, I spread, raked in and watered seed on the steeper slopes. I look forward to seeing it sprout in the coming weeks. Thanks for reading. I appreciate your comments.

Thursday, September 24, 2009

Day 87 and 88: More plaster preparation and drywall

I worked late again Wednesday. We did the same things as Tuesday, so that's my excuse for skipping a post. On Thursday, Trevor and I continued to prepare the walls for plastering while a crew installed drywall on the ceiling and interior walls. Here is a pic taken from the loft.

It is nice to see smooth clean surfaces replace the view of joists and insulation. About 6-1/2 inches of the curved glulam beams remains exposed. Thanks for reading. I appreciate your comments.

Tuesday, September 22, 2009

Day 86: More plaster preparation

I worked late today, so I am just posting a quick list of what was done.
  • Joshua completed installation of diamond mesh metal lath to the exterior of all windows, and to the interior of one window
  • I installed spray foam insulation around the interior of several 2nd story windows
  • Trevor continued to fill the slots containing electrical wiring and plumbing pipes with mortar
  • Marty tested spraying drywall joint compound and veneer plaster on the interior walls. More to come before the final decision on an interior finish.
Thanks for reading. I enjoy reading your comments.

Monday, September 21, 2009

Day 84 & 85: Final grading and plaster preparation

Joshua, Justin and I ran a successful test of a Tirolessa plaster gun on Friday. We shot the northeast corner wall with a coat of NHL 3.5 lime plaster from Saint Astier. Here is a vid of the gun in action.



Steve completed final grading around the home on Friday and Monday. Here is a pic of the home from the southwest.

Some of the other tasks started or completed Friday and Monday:
  • Trevor waterproofed the utility room retaining wall built Thursday
  • Justin and I completed application of weatherproofing on all windows
  • Joshua and I installed diamond mesh metal lath to the exterior of several more windows
  • I trimmed excess foam insulation around the interior of several windows
  • Erik completed all rough electrical wiring inside the home
  • Marty and Trevor filled slots containing electrical wiring and plumbing pipes with mortar to provide a uniform surface for plastering
  • Justin and Marty installed a vent pipe for the bathroom ventilation fan
I’ll close with a pic of Cindy cutting down scotch broom with her new electric hedge trimmer over the weekend. Thanks for reading. Please feel free to comment.