We did more plaster preparation tasks again Monday.
  • Joshua completed installing diamond mesh metal lath around the interior window frames
  • I applied masking tape and protective paper to 2 ledgers to prevent plaster contamination
  • Trevor set up scaffolding along the east wall
  • Trevor applied masking tape and plastic sheet to the exterior of the east windows and soffit
Here is a pic of the east wall almost ready for plastering

The spiral staircase from Stocklin Iron in Santa Rosa, CA was delivered today.