Monday, June 29, 2009

Day 35: Wall lift #2

We did some final preparations for wall lift #2 in the morning.
  • Positioned a seat for a porch roof beam.
  • Hung a pressure treated ledger for the loft from the east wall.
  • Finished placing all vertical rebar.
  • Placed J-bolt supports for the utility room north wall top plate.
  • Filled any gaps larger than 3/8 inch in the walls and around window bucks with closed cell spray foam to prevent grout from leaking out during the pour.
  • Added a few more metal bands around ledgers to keep them snug against the wall during the pour.
Pacific Coast Concrete Pumping and Las Anamas Concrete showed up after lunch.

The calm before the pour.

Justin and Marty getting ready for the hose.

Joshua, Justin, Marty and Trevor filled, consolidated, managed the hose and cleaned up - repeated for about 100 cores.

Raphael, doubling as Integral Construction staff photographer, was busy shooting photos.

I got to fill a few cells in the utility room.

We had another successful pour with no blowouts. Thanks for reading. I enjoy your comments.