Saturday, August 15, 2009

Day 66: Completed porch roof framing + 3 subs

On Friday, we completed installation of the reclaimed redwood tongue and groove flooring material on the porch roof framing. Here is a pic from northwest of the porch. It looks sweet!

Other tasks from day 66:
  • Trevor completed digging the trench to connect the main power to the utility room
  • Erik and Ryan continued to install electrical wiring
  • Tim and Carlos started installing the fire sprinkler system
  • The folks from Wildcat Metals were back again to install gutters on the main home. Here is a pic of the south wall of the home.
It is really exciting to see finish materials being installed. Thanks for reading. I enjoy reading your comments.