Saturday, August 15, 2009

Day 66: Completed porch roof framing + 3 subs

On Friday, we completed installation of the reclaimed redwood tongue and groove flooring material on the porch roof framing. Here is a pic from northwest of the porch. It looks sweet!

Other tasks from day 66:
  • Trevor completed digging the trench to connect the main power to the utility room
  • Erik and Ryan continued to install electrical wiring
  • Tim and Carlos started installing the fire sprinkler system
  • The folks from Wildcat Metals were back again to install gutters on the main home. Here is a pic of the south wall of the home.
It is really exciting to see finish materials being installed. Thanks for reading. I enjoy reading your comments.

Thursday, August 13, 2009

Day 65: Porch roof

Today we started installing the reclaimed redwood tongue and groove flooring material over the porch roof framing. Here is a pic looking up at the northwest corner.

Trevor continued digging a trench to connect the main power to the utility room. Erik and Ryan continued to install electrical wiring. Our thoughts are with the people fighting and affected by the Lockheed Fire. Thanks for reading. Feel free to leave a comment.

Wednesday, August 12, 2009

Day 64: Door installs, electrical wiring and porch framing

Today we installed the 2 remaining sliding glass patio doors. The highlight was the 600 pound 4 panel door in the family room.

Here is a pic of electrical wiring in process on the south wall of the great room.

Here is a pic of the porch framing nearly ready for the tongue and groove redwood flooring Cindy and I were planing and sanding a few weeks ago. We did a bit of cleanup today which is why you can actually see most of the porch.